Saturday, August 8, 2009

Kupe Gas Production Station. Sth Taranaki.NZ. 2009.

Leaving home for Sth Taranaki.

Looking over the truck load out. Deethaniser column. (right)

Sunrise at 7.ooam. Its going to be another great day.

The EWP makes work easy.

Lots of progress, the plant is really taking shape.

Snow down to low level this morning. It was cold but a beautiful day.

Slug catchers with the Tasman Sea beyond.

The Amine columns.

Looking over the tank farm and pipe rack 84.

A couple of good work mates.

Commissioning office.
.
Emergency flare stack.
.
Another view of Mt Egmont from the Kupe site.
.
On my day off I got a closer look at the mountain.